NESO Outlines Continued Challenge of Thermal Constraints in 2027 and Beyond

Executive Summary

  • The National Energy System Operator (NESO) has warned that costs of managing bottlenecks on the electricity network could almost double by this time next year, from £2bn to £3.9bn
  • The forecast for thermal constraints, where the grid cannot safely carry all available power because transmission lines are full, reflects an expectation of continued high gas prices, along with significant network constraints
  • While planned network outages are necessary to reinforce the network, NESO estimates 2027 thermal constraint costs would be 16% lower without them

 

The National Energy System Operator (NESO) has warned the cost of managing bottlenecks on the transmission network almost double this time next year – as high gas prices and network constraints continue to bite.

The operator, in its November 2026 Thermal Constraints Update report, put its short-term forecast at £3.9 billion in 2027, up from £2bn in the 2025/26 period. This reflects an expectation of continued high gas prices, alongside significant network constraints.

Planned network outages also play an important role; while necessary to reinforce the network, NESO estimates 2027 thermal constraint costs would be 16% lower without them. “That illustrates a tension in the transition: work to reduce constraints tomorrow can temporarily increase them today,” wrote NESO chief economist Mike Thompson.

Thermal constraints occur when the electricity grid cannot safely carry all available power because the transmission lines are full. These costs make up around two thirds of total balancing costs. NESO, alongside its partners, noted it saved £430m of thermal constraint cost in 2025/26, by making better use of existing network infrastructure, as well as expanding the tools available to manage constraints.

Costs are expected to remain high and get higher as 2030 approaches, before falling as major new network capacity comes online. The uncertainty associated with this – both from level and timing – means NESO publishes a range of projections rather than a single number.

The report identifies 26 initiatives in total across planning more strategically, improving market and operational signals, getting more from the network than currently, and unlocking more flexibility. One such way to get more out of the network is through dynamic line rating, increasing effective network capacity before new transmission routes are delivered, which NESO believes can save up to £1bn alone by 2030.

In total, balancing costs increased 16% in 2025/26 to £3.1bn, with a little under £0.5bn of that being paid to wind farms to turn down. The costs of keeping voltage steady and responding quickly to changes in supply and demand also rose. As Thompson noted, the increasing complexity of the system has to be considered. “For every unit of electricity the country uses, we’re now doing more than twice as much balancing as in 2018,” he wrote.

Picture credit: Envato/edlcsre

SPONSORED AD

Related Articles

SPONSORED AD
Popular Topics
Artificial Intelligence
Cooling
Data Centre Design & Build
Data Centre Infrastructure & Management
Markets & Leadership
Uninterruptible Power & Backup Systems
Opinion
Featured Articles
Gridlock in the gigawatt era: navigating the US utility bottleneck
Gridlock in the gigawatt era: navigating the US utility bottleneck
Gridlock in the gigawatt era: navigating the US utility bottleneck
Featured Resources
Capacitor failure in UPS systems
Capacitor failure in UPS systems
Capacitor failure in UPS systems

Sponsored

How Reliable Is Your UPS Infrastructure?
Learn how capacitor failures affect UPS performance and discover ways to reduce infrastructure risk.
SPONSORED AD