Executive Summary
- Ofgem has proposed the introduction of a new financial commitment for battery energy storage systems – with Britain currently having three times more battery capacity in the connections queue than the system is expected to need by 2035
- Under the proposal, projects would need to demonstrate a minimum level of financial commitment, starting at £3000 per MW, rising to a maximum of £25000 per MW if the queue remains significantly oversubscribed
- In August, Ofgem announced a similar commitment fee proposal to tackle what it called ‘speculative’ data centre projects
Ofgem has proposed a new commitment fee to help clear the connections queue for battery energy storage systems (BESS) projects – in a plan not dissimilar to one proposed to tackle speculative data centre projects announced the previous month.
The Oversubscribed Technologies Commitment Fee (OTFC) will help to ensure grid capacity is ‘held by projects that are serious about progressing’, the regulator noted. Under the proposal, projects would need to demonstrate a minimum level of financial commitment, starting at £3000 per MW, rising to a maximum of £25000 per MW if the queue remains significantly oversubscribed.
In April, Ofgem, alongside the Department for Energy Security & Net Zero, warned that queue formation outcomes highlight emerging risks for certain technologies, in particular a high volume of battery storage projects advancing to Gate 2 relative to the capacity ranges set out in the Clean Power 2030 Action Plan.
The OTCF will give the National Energy System Operator (NESO) responsibility for monitoring oversubscription levels, determining whether or when it is triggered or escalated, as well as managing projects’ financial securities. Ofgem noted that while NESO has cut 40% of grid-level battery capacity from the connections queue, 83GW is still prioritised on the new shortlist, alongside 7GW which is already operational.
In August, Ofgem announced a similar commitment fee proposal to tackle what it called ‘speculative’ data centre projects. The fee would be paid by large developments when accepting a connection offer, at 2.5% to 7.5% of average project costs, to be refunded when the project reached energisation and forfeited in the case of early exit. The consultation period ended last week.
Eleanor Warburton, director for energy system design and development at Ofgem, said that as Britain has three times more battery capacity in the connections queue than needed by 2035, identifying the projects which need to be built and the network infrastructure required remains difficult.
“The queue must reflect real projects, not placeholders,” said Warburton. “We are proposing approving the introduction of a new financial commitment to require battery projects to demonstrate they are serious about progressing, while encouraging those that are unlikely to connect to make that decision earlier.
“Britain needs the major deployment of large-scale battery storage to meet future electricity demand. These changes aim to create a more credible battery connections queue, so viable storage can connect, networks can invest with confidence, and consumers are not left paying for infrastructure that isn’t needed,” Warburton added.
Ofgem said it expects to publish its final decision later this year.